【边学边干】DIY装修Basement记录,(一)准备
【边学边干】DIY装修Basement记录,(二)搬运
【边学边干】DIY装修Basement记录,(三)钉木架(1)
【边学边干】DIY装修Basement记录,(三)钉木架(2)
【边学边干】DIY装修Basement记录,(三)钉木架(3)
【边学边干】DIY装修Basement记录,(三)钉木架(4)
【边学边干】DIY装修Basement记录,(四)Dry Wall (1)
【边学边干】DIY装修Basement记录,(四)Dry Wall (2) Taping
【边学边干】DIY装修Basement记录,(四)Dry Wall (3) 粉刷
粉刷完了Dry Wall之后,又用了一周多的时间铺了地板、装了门、钉了Base Board,现在就算初步完成了吧。当然门、Base Board还要油漆,但马上工作忙起来了,好在活不多了,有空的时候再做吧。
给大家看看与原先对比的效果:
Floor Plan:
![](http://farm3.static.flickr.com/2736/4457390005_b364762a4f_b.jpg)
从楼梯间开始:
![](http://farm5.static.flickr.com/4025/4458160272_5ee72283b3_b.jpg)
![](http://farm5.static.flickr.com/4030/4458145340_37232d6b9b_o.jpg)
楼梯左边的活动区A:
![](http://farm5.static.flickr.com/4033/4458165224_3a3bcdc407_b.jpg)
![](http://farm3.static.flickr.com/2710/4457383113_05084460be_b.jpg)
![](http://farm5.static.flickr.com/4025/4457367333_52301308c3_o.jpg)
![](http://farm5.static.flickr.com/4040/4457367163_aacd55045c_o.jpg)
![](http://farm5.static.flickr.com/4042/4457367769_133639ce24_o.jpg)
![](http://farm5.static.flickr.com/4037/4458146612_c5969c672d_o.jpg)
楼梯对面的活动区B:
![](http://farm5.static.flickr.com/4062/4458160862_bc3a89cac2_b.jpg)
![](http://farm3.static.flickr.com/2723/4458146938_c562f38a7e_o.jpg)
![](http://farm5.static.flickr.com/4013/4458147372_e4db580668_o.jpg)
![](http://farm5.static.flickr.com/4035/4457369203_1c6da81eb0_o.jpg)
![](http://farm3.static.flickr.com/2752/4458148700_cfb481f99a_o.jpg)
楼梯下的走廊:
![](http://farm5.static.flickr.com/4033/4457386489_4862658070_b.jpg)
![](http://farm5.static.flickr.com/4013/4458148982_da8afa034e_o.jpg)
![](http://farm3.static.flickr.com/2684/4458153578_dd81990906_o.jpg)
楼梯右边的长条形区域,我隔成了两部分:
![](http://farm3.static.flickr.com/2803/4457524763_a84874cb61_b.jpg)
办公室:
![](http://farm5.static.flickr.com/4064/4457371723_18d1d37d46_o.jpg)
![](http://farm3.static.flickr.com/2730/4458150466_221584633b_o.jpg)
![](http://farm5.static.flickr.com/4006/4458150686_e43e064b84_o.jpg)
![](http://farm3.static.flickr.com/2768/4457372391_894d5e40a0_o.jpg)
影音室:
![](http://farm3.static.flickr.com/2692/4457372669_b1ba5dd311_o.jpg)
![](http://farm3.static.flickr.com/2719/4458151388_4aea6cba94_o.jpg)
![](http://farm5.static.flickr.com/4068/4457373327_3acd72cb97_o.jpg)
![](http://farm5.static.flickr.com/4008/4458152040_3ed74e8539_o.jpg)
工程总花费:5451.22(含税)。
大致分类为:
工具:618.11
主要有:Miter Saw、Hummer Drill、梯子、万用表、Dry Wall T字尺等。
材料:3410.76
主要有:2X4 56根、2X3 221根、2X2 18根、Dry Wall 63片、复合地板 600平方尺、Base Board 182尺等。
照明:566.56
主要有:灯 12盏、电线 250米、插座、开关等。
Painting:478.41
主要有:防水漆 1桶、Dry wall Primer及涂料各2桶。
Hardware:377.39
主要有:木螺丝 约3000个、Dry Wall螺丝 约3000个、水泥钉、子弹、合页、拉手等。
前前后后加起来大约花了4个月的时间。